Northern Playground Basketball Court and Handball Court Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the basketball court, handball courts and add a drinking fountain to the public restroom building at Northern Playground.

Project Notes

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: December 2024
Completion Date: December 2024 (Design)

Procurement

Start Date: January 2026
Projected Completion Date: January 2027

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • City Council
  • Mayoral

Location

Northern Playground, Queens
Northern Boulevard and 93rd Street
Community Board: 03

 