Dyker Beach Park Bleachers Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the bleachers at Dyker Beach Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: April 2025
Projected Completion Date:
April 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Dyker Beach Park, Brooklyn
86th Street and Belt Parkway between 14th Avenue and 7th Avenue
Community Board: 10
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project