St. John's Recreation Center Pool Filter Plant Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the pool filter plant at St. John's Recreation Center.

Project Notes

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2024
Projected Completion Date: August 2024
Completion Date: July 2024 (Design)

Procurement

Start Date:

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

St. John's Park, Brooklyn
St. John's Recreation center
Community Board: 08

 

Project Staff

Project Liaison: Cristin Leoutsakos