Manhattan Community Garden Permeable Paver Installation
-
5% complete
-
0% complete
-
0% complete
This project will install permeable pavers.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: July 2025
Projected Completion Date:
February 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Locations
-
Brisas Del Caribe, Manhattan
237 East 3rd Street between Avenue B & C -
Allied Productions/Le Petit Versailles, Manhattan
247 East 2nd Street -
La Plaza Cultural, Manhattan
East 8th Street between Avenue B & C
Project Staff
Project Liaison: Cristin Leoutsakos