Metropolitan Recreation Center Dehumidification System Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the dehumidification system at the Metropolitan Recreation Center.
Project Notes
Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.
Project Timeline
Design
Assigned & Start Date: July 2024
Projected Completion Date:
February 2025
Completion Date:
March 2025
(Design)
Procurement
Start Date: August 2025
Projected Completion Date:
August 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Metropolitan Recreation Center, Brooklyn
261 Bedford Avenue
Community Board: 01
Project Staff