Metropolitan Recreation Center Dehumidification System Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the dehumidification system at the Metropolitan Recreation Center.

Project Notes

Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: February 2025
Completion Date: March 2025 (Design)

Procurement

Start Date: August 2025
Projected Completion Date: August 2026

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Metropolitan Recreation Center, Brooklyn
261 Bedford Avenue
Community Board: 01

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project