Fort Independence Playground Public Restroom Building Construction
-
30% complete
-
0% complete
-
0% complete
This project will construct the public restroom building in Fort Independence Playground.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: June 2025
Projected Completion Date:
June 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Independence Playground, Bronx
3600 Sedgwick Avenue
Community Board: 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks about this project