Renaissance Playground Public Restroom Building Construction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct the public restroom building in Renaissance Playground.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: June 2025
Projected Completion Date: June 2026

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Renaissance Playground, Manhattan
West 144th Street between Adam Clayton Powell Jr. Boulevard and Frederick Douglass Boulevard
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project