Haffen Park Community Center Construction
-
5% complete
-
0% complete
-
0% complete
This project will construct a field house in Haffen Park.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: July 2025
Projected Completion Date:
December 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Haffen Park, Bronx
Hammersley, Ely, Avenues
Community Board: 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks about this project