Riverside Park Drinking Fountains and Bottle Fillers Construction
-
30% complete
-
0% complete
-
0% complete
This project will construct drinking fountains and bottle fillers in Riverside Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: March 2025
Projected Completion Date:
March 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Riverside Park, Manhattan
Various locations between West 54th Street and West 96th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project