Manhattan and Bronx Emerald Ash Borer (EAB) Related Tree Removal FY25

  • Design
    40% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will remove trees hosted by Emerald Ash Borer (EAB) in Manhattan and Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2024
Projected Completion Date: January 2025
Completion Date: November 2024 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Various Locations, Manhattan and Bronx

Project Staff

Contact NYC Parks about this project