Tottenville Park Pool and Claremont Park Pool Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the pool.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2025
Projected Completion Date:
October 2025
Completion Date:
December 2025
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.