Francis Lewis Park Public Restroom Building Reconstruction
-
5% complete
-
0% complete
-
0% complete
This contract will reconstruct the public restroom building.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: December 2024
Projected Completion Date:
August 2025
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Francis Lewis Park, Queens
3 Avenue, 147 Street, East River, Parsons Boulevard
Community Board: 07
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project