Asser Levy Park Play Equipment Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the play equipment at Asser Levy Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2024
Projected Completion Date: November 2025
Completion Date: May 2025 (Design)

Procurement

Start Date: August 2025
Completion Date: December 2025 (Procurement)

Construction

Start Date: March 2026
Projected Completion Date: July 2026

Understand how we build parks.

Funding

Total Funding: $670,000
Funding Source: Mayoral

Location

Asser Levy Park, Brooklyn
West 5th Street, Sea Breeze Avenue, Surf Avenue
Community Board: 13

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project