Olmsted Center Ramp Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the ramp at the Olmsted Center.
Project Notes
Project Update: A date has been set for construction to begin.
Project Timeline
Design
The average time for design is 9-14 months. The design timeline for this specific contract will be established once the project scope is determined.
Procurement
Start Date:
Construction
Start Date: May 2025
Projected Completion Date:
November 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
117-2 Roosevelt Avenue
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project