Queens Tree-Damaged Sidewalk Reconstruction FY26 Community Boards 3 & 4
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 3 and 4 in Queens (renewal for QG-1623M).
Project Notes
Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2025
Projected Completion Date:
February 2026
Completion Date:
June 2025
(Design)
Procurement
Start Date: June 2025
Projected Completion Date:
June 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral