Cross Island Parkway Waters Edge Drive Playground and Public Restroom Building Construction
-
100% complete
-
0% complete
-
0% complete
This project will construct a public restroom building and playground and next to the Cross Island Parkway near Waters Edge Drive.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2021
Projected Completion Date:
April 2023
Completion Date:
August 2024
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Cross Island Parkway, Queens
24th Avenue and Waters Edge Drive
Community Board: 07, 11, 13
Project Staff
Project Liaison: Meira Berkower