Brooklyn Tree-Damaged Sidewalk Reconstruction FY23 (Renewal BG-923M) - Community Boards 3, 4, 5, 8, 9, 15, 16, 17, 18

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 3, 4, 5, 8, 9, 15, 16, 17 and 18 in Brooklyn.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2025
Projected Completion Date: January 2026
Completion Date: November 2025 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Various Locations, Brooklyn