Brooklyn Street Tree Planting FY27 - Community Boards 2-5, 8-10, 15-16

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will plant new and replacement tree in Brooklyn, Community Boards 2-5, 8-10, 15-16.

Project Notes

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Assigned & Start Date: January 2026
Projected Completion Date: November 2026

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Various Locations, Brooklyn