Queens Street Tree Planting FY27 (Renewal for QG-424M) - Community Boards 11-13
-
100% complete
-
0% complete
-
0% complete
This project will plant new and replacement trees in Community Boards 11-13 in Queens (Renewal for QG-424M)
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2026
Projected Completion Date:
November 2026
Completion Date:
January 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.