Crotona Park Pool Community Center Façade Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the façade of the Community Center at Crotona Park Pool.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2022
Projected Completion Date:
June 2025
Completion Date:
December 2025
(Design)
Procurement
Start Date: June 2025
Projected Completion Date:
November 2025
Completion
Date:
November 2025
(Procurement)
Construction
Start Date: January 2026
Projected Completion Date:
September 2027
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crotona Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project