Crotona Park Pool Community Center Façade Reconstruction
-
30% complete
-
40% complete
-
0% complete
This project will reconstruct the façade of the Community Center at Crotona Park Pool.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
The budget approval documents are currently under review by the NYC Office of Management and Budget.
Project Timeline
Design
Assigned & Start Date: August 2022
Projected Completion Date:
June 2025
Procurement
Start Date: June 2025
Projected Completion Date:
November 2025
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crotona Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project