Prospect Park Parade Ground Synthetic Turf Field 7&8 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf at Fields 7&8 at Prospect Park Parade Ground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2024
Projected Completion Date: December 2024
Completion Date: November 2024 (Design)

Procurement

Start Date: July 2024
Projected Completion Date: December 2024
Completion Date: November 2024 (Procurement)

Construction

Start Date: April 2025
Projected Completion Date: June 2025
Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $3,300,000
Funding Sources:
  • Mayoral
  • City Council

Location

Parade Ground, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project