Dyker Beach Park Synthetic Turf Fields Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf fields at Dyker Beach Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2024
Projected Completion Date:
December 2024
Completion Date:
November 2024
(Design)
Procurement
Start Date: August 2024
Projected Completion Date:
January 2025
Completion
Date:
November 2024
(Procurement)
Construction
Start Date: March 2025
Projected Completion Date:
July 2025
Completion Date: June 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Dyker Beach Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project