Washington's Walk Fort #4 Playground Basketball Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball court at Fort #4 Playground in Washington's Walk.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2023
Projected Completion Date:
May 2024
Completion Date:
April 2024
(Design)
Procurement
Start Date: July 2023
Projected Completion Date:
December 2023
Completion
Date:
April 2024
(Procurement)
Construction
Start Date: September 2024
Projected Completion Date:
April 2025
Completion Date: December 2024
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Washington's Walk, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project