Owl's Head Park Path Reconstruction, Phase 1
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the paths in Owl's Head Park, Phase 1.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2023
Projected Completion Date:
October 2024
Completion Date:
October 2024
(Design)
Procurement
Start Date: March 2024
Projected Completion Date:
August 2024
Completion
Date:
August 2024
(Procurement)
Construction
Start Date: March 2025
Projected Completion Date:
September 2025
Completion Date: July 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Owl's Head Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos