Owl's Head Park Path Reconstruction, Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the paths in Owl's Head Park, Phase 1.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: October 2024
Completion Date: October 2024 (Design)

Procurement

Start Date: March 2024
Projected Completion Date: August 2024
Completion Date: August 2024 (Procurement)

Construction

Start Date: March 2025
Projected Completion Date: September 2025
Completion Date: July 2025

Understand how we build parks.

Funding

Total Funding: $908,000
Funding Source: City Council

Location

Owl's Head Park, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos