Washington Market Park Pavement Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a portion of the pavement in Washington Market Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2024
Projected Completion Date:
June 2025
Completion Date:
June 2025
(Design)
Procurement
Start Date: October 2024
Projected Completion Date:
March 2025
Completion
Date:
June 2025
(Procurement)
Construction
Start Date: June 2025
Projected Completion Date:
October 2025
Completion Date: July 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Washington Market Park, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project