Kissena Corridor Park Synthetic Turf Soccer Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf soccer field at Kissena Corridor Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: November 2025
Completion Date: November 2025 (Design)

Procurement

Start Date: June 2024
Projected Completion Date: November 2024
Completion Date: October 2025 (Procurement)

Construction

Start Date: November 2025
Projected Completion Date: May 2026

Understand how we build parks.

Funding

Total Funding: $1,261,000
Funding Source: Mayoral

Location

Kissena Corridor Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project