Bronx Park Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the synthetic turf field at Bronx Park on Bronx Park East between Arnow Avenue and Britton Street.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
November 2025
Completion Date:
October 2025
(Design)
Procurement
Start Date: June 2024
Projected Completion Date:
November 2024
Completion
Date:
October 2025
(Procurement)
Construction
Start Date: November 2025
Projected Completion Date:
February 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bronx Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos