Ditmars Playground Multipurpose Play Area Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the multipurpose play area in Ditmars Playground.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2024
Projected Completion Date:
January 2025
Completion Date:
August 2025
(Design)
Procurement
Start Date: November 2024
Projected Completion Date:
April 2025
Completion
Date:
August 2025
(Procurement)
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: City Council
Location
Ditmars Playground, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project