Playground Twenty-One Multipurpose Play Area Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the multipurpose play area in Playground Twenty-One.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2024
Projected Completion Date:
January 2025
Completion Date:
July 2025
(Design)
Procurement
Start Date: November 2024
Projected Completion Date:
April 2025
Completion
Date:
July 2025
(Procurement)
Construction
Start Date: August 2025
Projected Completion Date:
December 2025
Understand how we build parks.