Alley Pond Park Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the paths surrounding the parking lot at 76th Avenue and Springfield Boulevard at Alley Pond Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2024
Projected Completion Date: January 2025
Completion Date: August 2025 (Design)

Procurement

Start Date: November 2024
Projected Completion Date: April 2025
Completion Date: August 2025 (Procurement)

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $732,000
Funding Source: Mayoral

Location

Alley Pond Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project