Wards Island Park Synthetic Turf Fields 82-85 Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct synthetic turf fields 82-25 at Wards Island Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2024
Projected Completion Date:
June 2025
Completion Date:
April 2025
(Design)
Procurement
Start Date: March 2025
Projected Completion Date:
August 2025
Completion
Date:
April 2025
(Procurement)
Construction
Start Date: May 2025
Projected Completion Date:
August 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Wards Island Park, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project