Randall's Island Park Synthetic Turf Fields 82-85 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct synthetic turf fields 82-25 at Randall's Island Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2024
Projected Completion Date: June 2025
Completion Date: April 2025 (Design)

Procurement

Start Date: March 2025
Projected Completion Date: August 2025
Completion Date: April 2025 (Procurement)

Construction

Start Date: May 2025
Projected Completion Date: August 2025
Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $5,331,000
Funding Source: Mayoral

Location

Wards Island Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project