Flushing Meadow Corona Park West Meadow Lake Forestry Compound Fence Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a fence at the Forestry compound on the west side of Meadow Lake in Flushing Meadow Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2024
Projected Completion Date:
February 2025
Completion Date:
October 2024
(Design)
Procurement
Start Date: October 2024
Projected Completion Date:
April 2025
Completion
Date:
October 2024
(Procurement)
Construction
Start Date: November 2024
Projected Completion Date:
February 2025
Completion Date: December 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project