Tudor Park Fence Reconstruction
-
30% complete
-
5% complete
-
0% complete
This project will reconstruct fencing at the playground at Tudor Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
NYC Parks staff members are currently reviewing the scope of the work order.
Project Timeline
Design
Assigned & Start Date: October 2025
Projected Completion Date:
July 2026
Procurement
Start Date: October 2025
Projected Completion Date:
March 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: State
Location
Tudor Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project