McLaughlin Park Retaining Walls Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct retaining walls along Tillary Street, Flatbush Avenue, and Cathedral Place in McLaughlin Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: September 2025
Completion Date: June 2025 (Design)

Procurement

Start Date: March 2025
Projected Completion Date: August 2025
Completion Date: August 2025 (Procurement)

Construction

Start Date: September 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

McLaughlin Park, Brooklyn

 

Project Staff

Project Liaison: Contact Us