Kissena Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will reconstruct retaining walls at the southwest corner of 164th Street and Oak Avenue in Kissena Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: September 2025
Completion Date: March 2025 (Design)

Procurement

Start Date: March 2025
Projected Completion Date: August 2025
Completion Date: August 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: February 2026

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Kissena Park, Queens

 