Kissena Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct retaining walls at the southwest corner of 164th Street and Oak Avenue in Kissena Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: September 2025
Completion Date: March 2025 (Design)

Procurement

Start Date: March 2025
Projected Completion Date: August 2025
Completion Date: August 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: February 2026

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral