Fort Washington Park Retaining Wall Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a retaining wall along Riverside Drive Service Road at West 161st Street in Fort Washington Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2024
Projected Completion Date:
September 2025
Completion Date:
April 2025
(Design)
Procurement
Start Date: March 2025
Projected Completion Date:
August 2025
Completion
Date:
June 2025
(Procurement)
Construction
Start Date: June 2025
Projected Completion Date:
December 2025
Completion Date: November 2025