Owl Hollow Fields Sports Lighting Fixture Replacement
-
100% complete
-
100% complete
-
0% complete
The scope of work shall be for the installation of LED lighting systems for athletic facilities at various Parks & Recreation locations, Citywide. Work is to include but is not limited to the removal of the existing bulbs, the purchase and installation of LED sports lights, requisite mounting and wiring, and photometric surveys.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
February 2026
Completion Date:
December 2025
(Design)
Procurement
Start Date: July 2025
Projected Completion Date:
December 2025
Completion
Date:
December 2025
(Procurement)
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Freshkills Park, Staten Island
Project Staff
Project Liaison: Cristin Leoutsakos