CPL Thompson Park Ballfield Lighting Fixture Replacement
-
30% complete
-
5% complete
-
0% complete
The scope of work shall be for the installation of LED lighting systems for athletic facilities at various Parks & Recreationlocations, Citywide. Work is to include but is not limited to the removal of the existing bulbs, the purchase and installation of LED sports lights, requisite mounting and wiring, and photometric surveys.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
NYC Parks staff members are currently reviewing the scope of the work order.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
June 2023
Procurement
Start Date: July 2025
Projected Completion Date:
December 2025
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral