Fort Tryon Park Retaining Wall Reconstruction at Fort Tryon Place
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct a retaining wall between Henry Hudson Parkway and Margaret Corbin Drive north of Fort Tryon Place in Fort Tryon Park.
Project Notes
Project Update: The work order is registered.
Project Timeline
Design
Assigned & Start Date: July 2024
Projected Completion Date:
October 2025
Completion Date:
October 2025
(Design)
Procurement
Start Date:
Completion
Date:
October 2025
(Procurement)
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.