Fort Tryon Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct a retaining wall between Margaret Corbin Drive and Broadway at Dongan Place in Fort Tryon Park.

Project Notes

Project Update: The work order is registered.

Project Timeline

Design

Assigned & Start Date: June 2024
Projected Completion Date: October 2025
Completion Date: October 2025 (Design)

Procurement

Start Date:
Completion Date: October 2025 (Procurement)

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Fort Tryon Park, Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project