Crotona Park Retaining Wall Reconstruction at Southern Boulevard
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct a retaining wall along Southern Boulevard between E175th Street and Crotona Park East in Crotona Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: September 2024
Projected Completion Date:
November 2002
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crotona Park, Bronx
Project Staff
Project Liaison: Contact Us
Contact NYC Parks about this project