Washington’s Walk Retaining Walls Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct retaining walls at the southeast corner of Claflin Avenue and Reservoir Avenue and along West 197th Street between Reservoir Avenue and University Avenue in Washington's Walk.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: November 2024
Projected Completion Date:
April 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.