Southern Fields Limited Scope Synthetic Turf Reconstruction
-
30% complete
-
5% complete
-
0% complete
This project will include construction fencing, temporary tree, and site protection measures, saw cutting, excavation, and removal of existing synthetic turf system, clearing and reconstruction of drainage structures and drain lines, broken stone, aggregates, concrete pavement and foundation materials, and installation of new synthetic turf system.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
NYC Parks staff members are currently reviewing the scope of the work order.
Project Timeline
Design
Assigned & Start Date: September 2025
Projected Completion Date:
September 2025
Procurement
Start Date: October 2025
Projected Completion Date:
March 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Lefferts Playground, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project