Marconi Park Limited Scope Synthetic Turf Reconstruction

  • Design
    30% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will include construction fencing, temporary tree, and site protection measures, saw cutting, excavation, and removal of existing synthetic turf system, clearing and reconstruction of drainage structures and drain lines, broken stone, aggregates, concrete pavement and foundation materials, and installation of new synthetic turf system.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Assigned & Start Date: September 2025
Projected Completion Date: September 2025

Procurement

Start Date: October 2025
Projected Completion Date: March 2026

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Marconi Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project