Saint Mary's Recreation Center Partial Reconstruction
-
90% complete
-
100% complete
-
0% complete
This project will reconstruct select areas in Saint Mary's Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2025
Projected Completion Date:
September 2025
Procurement
Start Date: September 2025
Projected Completion Date:
February 2026
Completion
Date:
November 2025
(Procurement)
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. Mary's Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project