Prospect Park (Maryland Monument) Path Reconstruction
-
0% complete
-
0% complete
-
0% complete
The reconstruction of pavement surface at Prospect Park (Maryland Monument) will include site work and removals (including construction fence and signage, tree protection measures, clear and grub, saw cutting, and excavation), asphalt pavement reconstruction, and concrete pavement reconstruction. .
Project Notes
Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.
Project Timeline
Design
The average time for design is 9-14 months. The design timeline for this specific contract will be established once the project scope is determined.
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Prospect Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project