Reconstruction of the Fencing Systems at Taqwa Community Farm
-
30% complete
-
40% complete
-
0% complete
Site work will include removing and replacing the existing eight-foot-high chain link fence around the perimeter of the garden, including the existing gated entrance on West 164th Street. In addition to removing fencing, some excavation is required for removal of the existing concrete footings for fence posts to be replaced by new concrete footings.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
The budget approval documents are currently under review by the NYC Office of Management and Budget.
Project Timeline
Design
Assigned & Start Date: October 2025
Projected Completion Date:
October 2025
Procurement
Start Date: October 2025
Projected Completion Date:
March 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council