Reconstruction of the Fencing Systems at Taqwa Community Farm

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

Site work will include removing and replacing the existing eight-foot-high chain link fence around the perimeter of the garden, including the existing gated entrance on West 164th Street. In addition to removing fencing, some excavation is required for removal of the existing concrete footings for fence posts to be replaced by new concrete footings.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: October 2025
Projected Completion Date: October 2025

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council