Baisley Pond Park 157th Street Playground Multipurpose Play Area Reconstruction

  • Design
    30% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This work will include site protection and construction fencing, removals, saw cutting and excavation, asphalt and concrete pavement, clear and reconstruct existing drainage piping and drainage structures, and landscape restoration work.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

The budget approval documents are currently under review by the NYC Office of Management and Budget.

Project Timeline

Design

Assigned & Start Date: November 2025
Projected Completion Date: October 2025

Procurement

Start Date: November 2025
Projected Completion Date: April 2026

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral