Flushing Meadows Corona Park Plumbing Reconstruction
-
30% complete
-
40% complete
-
0% complete
To facilitate the installation of water supply lines at Flushing Meadows Corona Park, the scope of work involves installing copper tubing, backflower prevention device (RPZ), curb valve, and property line valve. The process includes trenching through the street, sidewalk, and garden, followed by restoration of the path. The project aims to minimize impact on park features and avoid tree roots.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
The budget approval documents are currently under review by the NYC Office of Management and Budget.
Project Timeline
Design
Assigned & Start Date: November 2025
Projected Completion Date:
October 2025
Procurement
Start Date: November 2025
Projected Completion Date:
April 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project