Fort Totten Park Seawall Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the seawall in Fort Totten Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2009
Completion Date:
May 2012
(Design)
Procurement
Start Date: May 2012
Projected Completion Date:
February 2013
Completion
Date:
July 2013
(Procurement)
Construction
Start Date: August 2013
Projected Completion Date:
August 2014
Completion Date: August 2014
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Totten Park, Queens
Cross Island Parkway, Totten Road, Long Island Sound
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project